Eminent domain and water pipelines in Texas
When a city, water district or pipeline company wants to cross your land, Texas law sets out what they must offer, what they must tell you, and how the price gets decided.
Last updated Nov 17, 2026. By Ryan Trammell, Texas Hill Country. Sources are listed at the end of the page.
This is general information, not legal advice. Water law turns on the details. For your own land, talk to a Texas water lawyer, your groundwater district, or TCEQ. Read the full disclaimer.
When someone wants your land for water
Texas is building reservoirs, desalination plants and long pipelines to move water to growing cities. The Harbor Island desalination project is one example. Many of those projects cross private land, and the entities building them often have eminent domain power, the legal authority to take private property for public use if they pay for it.
Chapter 21 of the Texas Property Code sets the steps they must follow. Knowing those steps won't stop a project, but it does make sure you're treated fairly and paid what the law requires.
Step 1: The Landowner's Bill of Rights
The Texas Attorney General writes a Landowner's Bill of Rights that tells you that you have the right to notice of the proposed acquisition, a good-faith effort to negotiate, an assessment of your damages, a hearing including one on damages, and an appeal, among other rights. Gov't Code §402.031
An entity with eminent domain power has to give you that statement at least seven days before making a final offer. It also has to give it to you before or at the same time it first tells you, in any way, that it has eminent domain authority. Prop. Code §21.0112 If someone mentions condemnation and you haven't received it, ask for it.
Step 2: The initial offer and the final offer
Before going to court, the entity must make a "bona fide offer" to buy the property voluntarily. Prop. Code §21.0113 The law lays out what that means:
- A written initial offer that includes the Landowner's Bill of Rights, a bold statement of whether the price includes damages to the rest of your property or an appraisal, and a copy of the deed or easement they want you to sign. §21.0113(b)(1)
- A final offer made at least 30 days after the initial offer. §21.0113(b)(3)
- Before the final offer, a written appraisal from a certified appraiser of the property and any damage to your remaining land, and a final offer at least equal to that appraisal. §21.0113(b)(4)-(5)
- A copy of the appraisal and the conveyance, and at least 14 days to respond to the final offer. §21.0113(b)(6)-(7)
Pay attention to the easement language they hand you. For private entities, the law requires certain terms in some pipeline easements, and you're allowed to ask for different language. §21.0113(b)(1)(C)
Step 3: Special commissioners
If you don't agree, the entity can file a condemnation petition. The judge then appoints three disinterested property owners who live in the county as special commissioners to decide your damages, plus two alternates, within 30 days of filing. The judge gives preference to people both sides agree on. Prop. Code §21.014 Your Bill of Rights says you're entitled to a hearing, including one on the amount of damages, and to appeal a judgment in a condemnation case. Gov't Code §402.031 This is the stage where a lawyer and your own appraisal matter most.
Pipelines and your water
A pipeline easement is about the surface and the strip of land it crosses. It doesn't by itself transfer your groundwater, which stays your property. Water Code §36.002 If a project wants your water too, that's a separate deal, covered in our selling and leasing guide. Also ask how construction will handle your wells, stock tanks and fences, and whether the offer covers damage to the rest of your land.
Practical steps if you get a letter
- Keep every letter, email and voicemail, with dates.
- Check whether the Landowner's Bill of Rights was included. §21.0112
- Don't sign the first easement form you're handed. Read what it lets them do, how wide it is, and whether it can be used for other lines later.
- Consider your own appraisal, especially if the project splits a pasture or cuts off water.
- Talk to a Texas eminent domain lawyer before the 14-day window on the final offer runs out. §21.0113